WOW Talk about progress!
Ok, I have been super slack and have not updated the blog in a long time! Sorry! :) So for all those harassing me here is an update for you. :) In the last hmmmm weeks perhaps months since I have updated this, lots has happened! :) 1. All cornices, door frames, walls, skirtings, and window surrounds have been installed. 2. The kitchen has been installed 3. The kitchen has been tiled. 4. Both bathroom have been tiled and vanities/ vanitys ? installed. :) 5. The exterior of the house has been painted 6. The interior of the house has been painted. See, lots has been done! :) I still drive by daily and have met a few neighbours :) We have the electrics to be done, and the carpet and tiler are booked in for next Monday! :) It's all happening so fast! :) We work in school weeks and were originally told week 8 ( Tue) then it rained for 2 weeks so it has been pushed back until week 10 ( We have just started week 5). They seem to be flying through so who knows it may be earlier than expecte...